The Client
Turun teknologiakiinteistöt Oy
The Challenge
The tenant of the customer needed a new office that consisted of a reception, a meeting room, storage space and consultation rooms for customer appointments. The logistics of the site was considered challenging, since the new premises were on the 6th floor of an office building, and the material flow from the service elevator was through the office of another tenant. Because of this all hauling operations were to be kept at minimum.
The Solution
The new office was created with prefabricated element walls that are based on the modular Nuuk concept. Prefabricated elements were factory-equipped with socket and switch holes and even painted to match the preferred colors of the interior designer. By using a separate preassembly site a lot of time-consuming works could be carried out elsewhere, therefore reducing onsite logistics and need for manpower.